   Specifications
   Check компрессионного pressure in cylinders and tightness of the block
   Diagnostics of a condition of the engine with vacuum gauge application
   System of greasing of the engine - the general information
   - The procedures of the repair which has been not connected with extraction of the engine from the car, - four-cylinder engines
      Reduction of the piston of the first cylinder in position ВМТ
      Check and adjustment клапанных backlashes
      Removal and installation of a pulley of a cranked shaft
      Removal and installation of forward covers of drive ГРМ
      Removal and installation of a belt of drive ГРМ, check of a condition of components
      Removal, check of a condition and installation of cogwheels of camshafts
      Removal and installation of a cogwheel of a cranked shaft
      Натяжитель газораспределительного a belt - the general information and a functioning principle
      Removal, check of a condition and installation of elements of a drive of valves
      Removal and installation of camshafts
      Removal and installation of heads of cylinders
      Removal and pallet installation картера and маслозаборника
      Removal, service and installation of the oil pump
      Check of pressure of impellent oil
      Removal and installation of the gauge-switch of pressure of oil
      Removal, check of a condition and installation of a flywheel/privodnogo of a disk
      Replacement of support of a suspension bracket of the power unit
   + The procedures of the repair which has been not connected with extraction of the engine from the car, - six-cylinder engines
   + The general and major repairs of engines
+ Systems of cooling, heating
+ The power supply system and release
+ Engine electric equipment
+ Manual box and differential
+ Automatic transmission
+ Coupling
+ Brake system
+ Suspension bracket and steering
+ Body
+ Onboard electric equipment


8eee0de7



Removal, check of a condition and installation of elements of a drive of valves

Arrangement of components of a drive of valves

1 — the Adjusting screw коромысла with a lock nut
2 — Koromyslo of a drive of the inlet valve
3 — the Wavy washer

4 — the Case of camshafts
5 — the Support
6 — Koromyslo of a drive of the inlet valve


Details of installation of components of a drive of valves

1 — Koromysla of a drive of inlet valves
2 — the Lock nut
3 — the Adjusting screw
4 — the Spring
5 — the Basic plug of an axis коромысел
6 — the Axis коромысел a drive of the inlet valve
7 — the Axis коромысел a drive of the final valve

8 Koromysla of a drive of final valves

Efforts of a tightening of carving connections, Nanometer

Т1: 5
Т2: 10
Т3: 25


The arrangement of components of assemblage коромысел is shown on an illustration.

To detail of installation of components of assemblage коромысел it is shown on an illustration.

Коромысла a drive of inlet and final valves are established on their own axes which with the first are kept in joint assemblage by covers of heads of cylinders.

The end of everyone коромысла from outside the valve is supplied by the adjusting screw and a nut. By means of turn of this screw it is possible to regulate клапанный a backlash.

Forked коромысла final valves operate simultaneously two final valves.

REMOVAL

 PERFORMANCE ORDER

1. Remove a V-shaped belt (Routine maintenance see the Head).
2. Remove a pulley of a cranked shaft (see Has undressed Removal and installation of a pulley of a cranked shaft).
3. Uncover drive belt ГРМ (see Has undressed Removal and installation of forward covers of drive ГРМ).
4. Remove assemblage of belt ГРМ (see Has undressed Removal and installation of a belt of drive ГРМ, check of a condition of components).
5. Remove a camshaft cogwheel (see Has undressed Removal, check of a condition and installation of cogwheels of camshafts).
6. Disconnect a ventilation hose картера (PCV) and uncover heads of cylinders (see Has undressed Removal and installation of heads of cylinders).

7. Operating in an order, the return shown on an illustration, release and turn out bolts of fastening of assemblage коромысел.


 For assemblage deduction at last stage leave pair of average bolts screwed on pair coils of a carving.


8. Accurately take assemblage коромысел.

DISMANTLING

 PERFORMANCE ORDER

1. Turn out bolts of fastening of an axis коромысел.
2. Take an axis коромысел. Remove from an axis коромысла, springs, plates and basic plugs, - removed components put as their installation.
3. Release nuts and turn out from коромысел adjusting screws.

CHECK

 PERFORMANCE ORDER

1. Measure internal diameters коромысел and external diameter of an axis коромысел in corresponding points. By subtraction of results of the second measurements from corresponding results of the first define sizes of oil backlashes. Compare results of measurement to requirements of Specifications, replace the worn out components.

2. Measure internal diameters of basic plugs (holders) of an axis коромысел and external diameter of an axis коромысел in corresponding points and define sizes of oil backlashes. Compare results of measurement to requirements of Specifications, replace the worn out components.
3. Attentively examine workers (contacting to cams of a camshaft and cores of valves) surfaces коромысел. In case of revealing of jags, задиров and signs of excessive deterioration replace defective components.
4. Check up smoothness of rotation of rollers коромысел. Replace defective components.
5. Visually study a condition of components редукционного the valve in a face part of an axis коромысел. In case of revealing of cracks on a control ball, alien particles on coils of a spring or signs of development of leaks, replace the failed components, or an axis коромысел in gathering.

ASSEMBLAGE

 PERFORMANCE ORDER

Assemblage is made in an order, the return to a dismantling order. Track, that bolts of fastening of basic plugs of an axis коромысел have been tightened with demanded effort (5 Nanometers).

 Коромысла, their axes and a support of axes are marked by identification labels, - track correctness of installation of components!

INSTALLATION

 PERFORMANCE ORDER

1. Establish assemblage on the place and temporarily tighten bolts with 1 on 4 in the order specified in illustrations with uniform effort.

2. Tighten with demanded effort (25 Nanometers) bolts with (5) on (8).
3. Tighten with demanded effort (25 Nanometers) bolts with (1) on (4).

4. Make adjustment клапанных backlashes (the Section Check and adjustment клапанных backlashes see).
5. The further installation is made in an order, the return to an order of dismantle of components